HelioExpect
    UPC Renewables · Rajasthan

    A month of DSM exposure, measured block by block.

    A full month on a 100 MW AC plant in Rajasthan, measured across 1,661 settlement blocks, with deviation charges reconciled against generation revenue.

    ClientUPC Renewables
    SiteSitara Solar
    MarketRajasthan, India
    Capacity100 MW AC
    Period1–31 July 2026
    0.19%
    DSM loss vs revenue
    6.83%
    Normalised MAE
    27.98%
    P95 deviation
    1,661
    Blocks measured

    Deviation band distribution across 1,661 blocks

    Blocks per band by absolute deviation across the window. This is the measured distribution for July 2026, not a comparison against a previous period.

    Context

    Sitara Solar is a 100 MW AC plant in Rajasthan settling under state DSM. Over July 2026 the site was measured across 1,661 fifteen-minute settlement blocks, every one scored for deviation against schedule.

    What we did

    Day-ahead and intraday forecasting at 15-minute resolution, with deviation attributed per block and rolled up by band so exposure could be read by cause rather than by date.

    Result

    Deviation charges over the month came to ₹128,084 against generation revenue of ₹66,995,236 — 0.19% of revenue.

    Normalised MAE across the month was 6.83%, with the best day at 4.71% and the worst at 11.47%. P95 deviation averaged 27.98%.

    Of 1,661 blocks, 967 sat inside the 0–10% band. 295 blocks exceeded 20%, and those are where the charge concentrates.

    DSM economics

    Revenue loss
    0.19%
    Penalty after
    ₹128084.31

    The applicable deviation settlement regulation is not recorded for this site.

    Deviation band detail

    Deviation bandBlocks
    0–10%967
    10–15%222
    15–20%177
    >20%295

    Operational impact

    • Deviation attributable by block and band rather than as a monthly total
    • The >20% band isolated as the target for schedule optimisation
    • Accuracy tracked daily, so drift is visible within the month rather than after it

    Next steps

    The >20% band carries disproportionate charge relative to its block count. Ramp-event handling and intraday revision cadence are the two items that address it.

    Talk to the team

    Methodology

    Window 1–31 July 2026, 1,661 fifteen-minute blocks, 31 days with data.

    Accuracy is reported as normalised MAE: absolute error divided by MQmax, the maximum actual generation for that day. This is the backend's `MAPE` field under its true definition. A textbook MAPE, which divides by per-block actual, would read very differently on the same data.

    Deviation charges are computed at a PPA rate of ₹3500/MWh. No prior scheduling baseline has been measured on this site, so no reduction is claimed.

    No days were excluded. Every day in the window had a complete feed.

    Blocks
    1661 × 15 min
    Denominator
    MQmax — maximum actual generation for the day